DENIOS designed six heating chambers for a producer of special chemicals located in Wesel, Germany. The insertion through a 28m high up erection opening presented a particular challenge.
A producer of special chemicals located in Wesel, Germany required six heating chambers with especially high capacities and short warm-up times to achieve maximal throughput. Different material properties and resulting special requirements and local conditions demanded an anything but commonplace solution.
In an effort to adjust the chambers to the narrow space conditions, building sketches had to be taken into account during the planning phase. The usual gate structure consisting of double doors was not an option due to the narrow aisle width. As sliding doors are not suitable for 4m high chambers, roll-up doors have been installed.
The circulation fan stops automatically when the doors roll up. This way not only the installation room but also the members of staff are protected from evaporations that are potentially hazardous to health. Due to this measures, the chambers' explosion protection could be reduced from zone 1 to zone 2.
The already existing steam system has been used as the chambers' heating element. The chambers are operated with recirculating air.
Sump pallets in compliance with the Water Protection Act meet all regulations concerning water law requiring units in which substances are handled to be as secure as storage units.
Making the most out of the confined space in the showroom was not the only challenge that presented itself.
Furthermore, the chamber had to be lowered through an erection opening in the roof of the building, 28m up in the air. Owing to its size, the chamber had to be apportioned in the middle.
The roll-up door could not remain in the upper half of the chamber due to the unbalanced weight distribution that would cause. As a result, all six chambers had to be lifted into the building in three individual parts each. They were assembled on-site and moved to their designated place in the production hall.
Assembling the units on-site in just a week was possible thanks to the systems' "plug and store" design. The chambers' throughput of substances has been significantly increased compared to the previous solution.
The complete documentation including the CE marking, ATEX certificate of conformity, operating instructions, ect. were send to the costumer directly subsequent to the acceptance protocol procedures. This ensured that the system could be brought on line expeditiously.
This examples portrays how important experience and approved systems are when planning and designing units for hazardous substances. Many regulations, rules and requirements have to be met to ensure a safe system. Strong partners who suit their clients' needs and offer a wide range of solutions, save time and expenses and ensure law compliant solutions with lowest possible hazards
Give us a call or fill out the form and we will get back to you as soon as possible.
Use code DEN10 at checkout for 10% off ALL of our catalogue products. Cannot be combined with other promotions, discounts or other special prices. Does not apply to open quotations.